Backward scheduling: the tightest document is not always the slowest one

Type your own internal date and each document walks backward from it: time to produce, time to travel, time for you to read it, time to put it right. The date its request has to leave falls out of that, and so does the margin. On the sheet this page opens with, the smallest margin sits on the shortest chain.

Live result

Commercial invoice has the least margin on this sheet, and its request can leave no later than 27 March.
  • your internal date1 April
  • margin left on it1 working day
  • documents on the sheet6
The shortest chain runs out first, and the plan behind it decides when the request leaves.
S=D−LS=D-LS=D−L
where SSS is 27 Mar, DDD 1 Apr, and LLL 3 working days.
m=S−Pm=S-Pm=S−P
where mmm is the margin in working days and PPP 26 Mar. · pack front 13 Mar, 13 working days out
Commercial invoice has the least margin on this sheet, and its request can leave no later than 27 March.The shortest chain runs out first, and the plan behind it decides when the request leaves.

Your internal date

Try a plan

Your planning date, against which every margin is measured.

Non working days

One working week applies to the whole chain.

The document in focus

These day counts are an example. Replace them with your own.

working days

The time between the request arriving and the document existing.

working days

The document's courier time to your desk.

working days

The time you take to read the document before sending it.

working days

Time reserved for a correction round trip.

Commercial invoice
Ask by 27 Mar · 1 working day spare
Transport document
Ask by 23 Mar · 2 working days spare
Packing list
Ask by 27 Mar · 3 working days spare
Legalised invoice copy
Ask by 13 Mar · 3 working days spare
Certificate of origin
Ask by 18 Mar · 4 working days spare
Inspection certificate
Ask by 13 Mar · 6 working days spare

The table above is authoritative for the current inputs and stays in least margin order.

Six documents working back to one date

Live chart
Six documents working back to one dateWorking back from 1 April, Commercial invoice is the document with least margin: its request can leave no later than 27 March, which is 1 working day ahead of the date you planned to ask. It has the shortest chain of the 6 on this sheet. Six chains from three to thirteen working days. First request leaves 13 March. Internal date 1 April. Least margin one working day, on the commercial invoice.Commercial invoice1 working dayPacking listTransport documentCertificate of originInspection certificateLegalised invoice copyyour internal date · 1 Aprfirst request leaves · 13 Maryour internal date · 1 Aprfirst request leaves · 13 Mar27 Feb19 Mar8 AprThe scenario calendar

Why the shortest chain runs out first

A chain length belongs to a document, while a margin belongs to a plan, and nothing links the two automatically.

Long chains attract early requests while short chains are often left late.

The correction allowance therefore stays separate from production so its protection remains visible.

What a margin is not

A margin is the working days between a planned request and the last date the typed chain permits. It is not a rule period, contractual float or time anybody owes you.

The smallest margin names the tightest document but not necessarily the one controlling the outcome. The date is only as accurate as the typed duration estimates.

Correction allowance, Commercial invoice

working days
working days
working days
working days

It does not check the values in between.

How the answer sits across the values sampledA rail of the 13 values sampled, from 0 working days to 12 working days in steps of 1 working day. Across the values sampled, the document with the least margin stays Commercial invoice from 1 working day to 12 working days, the highest value sampled. The nearest value where it changes is 0 working days, where it becomes Transport document.first change0 working days1 working dayon the page

Across the values sampled, the document with the least margin stays Commercial invoice from 1 working day to 12 working days, the highest value sampled. The nearest value where it changes is 0 working days, where it becomes Transport document.

Across the values sampled, the document with the least margin stays Commercial invoice from 1 working day to 12 working days, the highest value sampled. The nearest value where it changes is 0 working days, where it becomes Transport document.
The answerCommercial invoice
Values sampled0 working days to 12 working days, 13 values, step 1 working day
Holds from1 working day
Holds to12 working days, highest sampled
Nearest value that changes it0 working days
The answer thereTransport document

What an unchanged region does and does not prove is set out in a short lesson.

The sweep samples only the values you entered. Between samples the answer is not checked, so read the boundary as observed, not proven.

Here is the maths

▾

The formula, in words

  • One document is four spans laid end to end, and every one of them is counted in working days. The time to produce it, the time for it to reach your desk, the time you take to read it, and the time held back for the round trip if it comes back wrong. Added together they are the chain. Subtracted from your internal date, walking backward over working days only, they give the last date the request can leave.
  • The margin is the distance between two dates and belongs to your plan. It is the working days between the date you wrote down that you would ask and the last date the chain leaves room for. It is not a rule period and it is not float in any contractual sense. Where the planned date falls later than the last safe date the margin is reported as a negative number rather than clamped to zero, because the state a sheet like this exists to surface is exactly that one.
  • Chain length and margin are computed from different things and do not have to agree. A chain is a property of a document and of whoever issues it. A margin is a property of a plan, and a plan is written by whoever was worried. On the sheet this page opens with, the ranking by chain and the ranking by margin are close to reversed.
  • The pack runs in parallel, so it is never a sum. Six chains totalling forty nine working days occupy thirteen working days of calendar, because six requests are in the post at the same time. The number that matters is the earliest of the six last safe dates, and it is the only figure on the sheet that describes the pack rather than a document.

A worked example

The calendar. 1 March is a Sunday in this scenario. Saturdays and Sundays are the non working days on the default setting. No public holiday exists on this page.

The internal date. 1 April, a Wednesday, as typed. It is the visitor's own date. Nothing on this page proposes it and nothing checks it.

Walking backward. Counting working days back from Wednesday 1 April gives the ladder every latest safe date is read off.

backdate
131 Mar Tue
230 Mar Mon
327 Mar Fri
426 Mar Thu
525 Mar Wed
624 Mar Tue
723 Mar Mon
820 Mar Fri
919 Mar Thu
1018 Mar Wed
1117 Mar Tue
1216 Mar Mon
1313 Mar Fri
1412 Mar Thu
1511 Mar Wed
1610 Mar Tue
179 Mar Mon
186 Mar Fri
195 Mar Thu

The six chains, and where each request has to leave.

Documentprodtranrevcorrchainask byplan to askmargin
Commercial invoice1011327 Mar Fri26 Mar Thu1
Packing list1011327 Mar Fri24 Mar Tue3
Transport document3112723 Mar Mon19 Mar Thu2
Certificate of origin42131018 Mar Wed12 Mar Thu4
Inspection certificate62231313 Mar Fri5 Mar Thu6
Legalised invoice copy53141313 Mar Fri10 Mar Tue3

One row read out loud. The commercial invoice takes one working day to produce, no transit because it never leaves the building, one working day for somebody to read it, and one held back in case it comes back wrong. Three working days. Three working days back from Wednesday 1 April is Friday 27 March. The plan says ask on Thursday 26 March. Between those two dates there is exactly one working day, and that is the whole margin on the document nobody was worried about.

The rank inversion, stated. Sorted by chain, longest first: inspection 13, legalised copy 13, certificate of origin 10, transport 7, invoice 3, packing list 3. Sorted by margin, smallest first: invoice 1, transport 2, packing list 3, legalised copy 3, certificate of origin 4, inspection 6. The document at the top of the first list is at the bottom of the second. The chain is a fact about the document. The margin is a fact about the plan. They were never the same question.

The front of the workback. The earliest of the six latest safe dates is Friday 13 March, shared by the inspection certificate and the legalised copy. That is thirteen working days before the internal date, and thirteen working days here span nineteen calendar days: 13 March to 1 April. Six of those nineteen are Saturdays and Sundays. Six days of the pack's runway are days on which nobody was going to do anything.

The number that explains why the sheet is a sheet. The six chains add to forty nine working days of document time. The pack takes thirteen. The difference is not efficiency, it is parallelism: six requests are in the post at once. This is also why the workback is computed per document and never as a total, and why a single lead time for the pack would be the wrong number by thirty six working days.

The check that makes it stick. Switch the non working days from Saturday and Sunday to Friday and Saturday. Four of the six latest safe request dates move and two do not. Not one of the six margins changes.

DocumentSat and SunFri and Satmargin
Commercial invoice, chain 327 Mar Fri29 Mar Sun1
Packing list, chain 327 Mar Fri29 Mar Sun3
Transport document, chain 723 Mar Mon23 Mar Mon2
Certificate of origin, chain 1018 Mar Wed18 Mar Wed4
Inspection certificate, chain 1313 Mar Fri15 Mar Sun6
Legalised invoice copy, chain 1313 Mar Fri15 Mar Sun3

Five working days is seven calendar days under either convention, so the two counts stay in step and only part company where a chain ends on a Friday or a Sunday. The convention decides which dates are closed. It does not decide how much room you have.

The three chips, and what each one proves.

Documentdefaultinspection ×2\times 2×2no correctiondate out a week
Commercial invoice1126
Transport document2247
Packing list3348
Legalised invoice copy3378
Certificate of origin4479
Inspection certificate60911
least margin sits onCommercial invoiceInspection certificateCommercial invoiceCommercial invoice

Chip 1 doubles the inspection certificate's production from six working days to twelve, taking its chain from thirteen to nineteen and its margin from six to zero. The slowest document becomes the tightest only after its production doubles, and at that point it has no room at all. Chip 2 removes every correction allowance, which grows every margin and leaves the tightest document exactly where it was: the correction allowance is not what makes the invoice tight, the planned request date is. Chip 3 moves the internal date out five working days, which adds five to all six margins and changes nothing about their order, because the order is a property of the plan and not of the deadline.

Check it yourself

Switch the non working days to Friday and Saturday. Four of the six latest safe dates move and two stay, and none of the six margins changes. Five working days span seven calendar days in both conventions, so the two counts move together and separate only where the chain ends on a Friday or a Sunday. The convention decides which dates are closed. It does not decide how much room you have.

What this does not model

Any period or framework date set by somebody else; whether a late request earns anything, which is a question about the words in a contract; how anybody will treat a document; a public holiday of any kind, in any place; two different working weeks on one sheet, which is what a chain crossing two places actually needs, and which would also break the single margin ranking this page reports; a document whose chain shares a person with another document's chain, where the binding constraint is the person and not the smallest figure; more than one correction round; a correction round that cannot begin until somebody says what is wrong, which is real elapsed time this sheet folds into its correction span rather than counting; the pooling of correction time at the end of the pack instead of per document, which is what the critical chain literature argues for and the opposite of what this sheet does; a request that goes out and is never answered; documents beyond six; the derivation of any date from any particular document, which decides what a real chain would count from; and the accuracy of any day count typed into it, all of which are estimates until the issuer has been asked.

Equation trace

  1. Add production, transit, review, and correction to obtain each document chain.
  2. Walk that chain backward from the internal date using the selected working week.
  3. Subtract the planned request date from the latest safe date to obtain margin.
  4. Order valid rows from the least margin upward without changing the underlying document record.

Boundary

The internal date is a planning input rather than a rule period or right to time, one working week applies to every chain, public holidays are outside the model, and parallel requests are not added together.

Source anchors

  • Project Management Institute scheduling standards. Describes published scheduling practice used as context for backward planning.
  • International Chamber of Commerce documentary credits overview. Identifies the documentary credit framework that makes the actual required documents source specific.

Calculation version

1.0.0

The whole record prints. Your browser can save it as a PDF instead of printing it.

This page counts working days backward from a date you typed and reports how much of your own plan is left in front of each request. That date is yours: it is not a rule period, it is not a deadline set by any framework, and no rule period appears anywhere on this page or on the sheet it prints. Which documents a shipment needs, and how long each of them takes, comes from the contract and the credit in front of you; the six on the default sheet are an example to overwrite and every day count on them is invented for this page. The method is described from the documentary credit literature and from published scheduling practice, and no text from any of those sources appears here: the mechanisms are described in this page's own words and the sources are named where they are used. Nothing here reports how anybody will treat a document or says anyone is owed time.

Related

  • Claim preparation: assemble a packet and hear what a reviewer asksPick the evidence, do the arithmetic, and a reviewer walks the packet naming what is missing, what does not agree with something else in it, and what a real one would ask next. There is no mark at the end, because a reviewer does not give one.Interactive lesson · 6 min

DOCUMENT REQUEST WORKBACK

YOUR INTERNAL DATE

1 April, a WednesdayYour own date. Every margin on this sheet is measured against it and against nothing else.

NON WORKING DAYS

Sat and SunOne working week, counted in one place.

THESE NUMBERS

These day counts are an example. Replace them with your own. The day counts below are the ones you typed. Replace them with figures from the people who issue these documents.

THE PACK

6 documents · first request leaves 13 Mar13 working days to the internal date19 calendar days, 6 of them non working49 working days of document time in total, because the requests run beside each other

THE WORKBACK

Documentask bymarginprodtranrevcorrchainCommercial invoice27 Mar110113Transport document23 Mar231127Packing list27 Mar310113Legalised invoice copy13 Mar3531413Certificate of origin18 Mar4421310Inspection certificate13 Mar6622313

margins and spans are working days, and rows are in margin order, tightest first

LEAST MARGIN

Commercial invoice, 1 working daythe shortest chain on the sheet

Sweep of Correction allowance, commercial invoice

The assumption
Correction allowance, commercial invoice
Values sampled
0 to 12 working days, 13 values, step 1
The answer
Commercial invoice holds the least margin
Holds across
1 to 12 working days
Nearest change
0 working days, where it becomes Transport document
Reading the boundary
The sweep samples only the values you entered. Between samples the answer is not checked, so read the boundary as observed, not proven.

Field record

The table above is authoritative for the current inputs and stays in least margin order.
Commercial invoice: 27 Mar, 1; Transport document: 23 Mar, 2; Packing list: 27 Mar, 3; Legalised invoice copy: 13 Mar, 3; Certificate of origin: 18 Mar, 4; Inspection certificate: 13 Mar, 6
Equation trace
Add production, transit, review, and correction to obtain each document chain. Walk that chain backward from the internal date using the selected working week. Subtract the planned request date from the latest safe date to obtain margin. Order valid rows from the least margin upward without changing the underlying document record.
Boundary
The internal date is a planning input rather than a rule period or right to time, one working week applies to every chain, public holidays are outside the model, and parallel requests are not added together.
Source anchors
Project Management Institute scheduling standards; International Chamber of Commerce documentary credits overview
Calculation version
1.0.0
The printed workback uses the same inputs, calculation, ordering, and margins shown on screen.
The printed workback uses the same inputs, calculation, ordering, and margins shown on screen.

TO FILL IN

Documentissueroriginalsasked onpromisedarrivedCommercial invoiceTransport documentPacking listLegalised invoice copyCertificate of originInspection certificate

WHAT MOVED

This page counts working days backward from a date you typed and reports how much of your own plan is left in front of each request. That date is yours: it is not a rule period, it is not a deadline set by any framework, and no rule period appears anywhere on this page or on the sheet it prints. Which documents a shipment needs, and how long each of them takes, comes from the contract and the credit in front of you; the six on the default sheet are an example to overwrite and every day count on them is invented for this page. The method is described from the documentary credit literature and from published scheduling practice, and no text from any of those sources appears here: the mechanisms are described in this page's own words and the sources are named where they are used. Nothing here reports how anybody will treat a document or says anyone is owed time.