Date constraint: the delay in front of the date stopped travelling

One activity carries a fixed start date and its predecessor runs 26 days late. Under the fixed date none of the delay reaches completion, and read as not earlier than, 17 days walk through.

Live result

Under a fixed start, 26 delay days stop at the successor and completion moves 0 days.
  • actual predecessor finish2026-02-06
  • overlap the sequence does not support17 days
A fixed start holds the date by pushing the delay into an overlap nobody typed.
Under a fixed start, 26 delay days stop at the successor and completion moves 0 days.A fixed start holds the date by pushing the delay into an overlap nobody typed.

Try a record

2026-02-06date

This is the one date moved by the chart and the exact daily sweep.

Tracked date reading

Edit the chain and sweep dates▾
Predecessor
days
Successor
days
Relationship
Finish to start
Exact daily sweep
Tracked reading
Fixed start
Delay stops at
Frame
First tracked change below
2026-02-05
First tracked change above
2026-02-07

Two date readings and the exact daily sweep

Live chart
The same chain under two date readingsThe actual predecessor finish is 2026-02-06. Under fixed start the successor completes on 2026-01-25 with 17 unsupported overlap days. Under not earlier than it completes on 2026-02-11 with 17 delay days reaching completion.constraint datefixed startmodel completionunsupported bytyped sequenceactual predecessorfinishnot earlier thantyped target2026-01-112026-01-272026-02-11
Live chart
Delay reaching completion at every finish date in the sweepEvery civil date from 2026-01-05 through 2026-02-10 is evaluated. Fixed start sends zero predecessor delay days to completion. Not earlier than sends days after the constraint date to completion.01121whole delay days reaching completion2026-01-052026-02-10actual predecessor finish datefixed startnot earlier thandelay reaches completion

fixed start

Successor start
2026-01-20
Completion
2026-01-25
Completion movement
0 days
Delay stopped
26 days
Delay reaching completion
0 days
Unsupported overlap
17 days
Predecessor total float
−17 days
Successor total float
16 days

not earlier than

Successor start
2026-02-06
Completion
2026-02-11
Completion movement
17 days
Delay stopped
9 days
Delay reaching completion
17 days
Unsupported overlap
0 days
Predecessor total float
−1 day
Successor total float
−1 day
Both date readings
MeasureFixed startNot earlier than
Successor start2026-01-202026-02-06
Completion2026-01-252026-02-11
Completion movement0 days17 days
Delay stopped26 days9 days
Delay reaching completion0 days17 days
Unsupported overlap17 days0 days
Predecessor total float−17 days−1 day
Successor total float16 days−1 day

This reads the dates, durations, target, and finish to start relationship typed by the visitor. It does not decide whether a date constraint is proper, whether an overlap could be worked, who carries delay, whether time or money follows, or what any schedule specification requires.

Here is the maths

▾

The formula, in words

Treat every date as an exclusive civil day boundary. Planned predecessor finish is planned start plus predecessor duration. Fixed start always places the successor on the constraint date. Not earlier than places it on the later of the constraint date and predecessor finish. Successor completion is its resulting start plus its duration.
Fp=Sp+dpF_p=S_p+d_pFp​=Sp​+dp​
where FpF_pFp​ is planned predecessor finish, SpS_pSp​ planned predecessor start, and dpd_pdp​ predecessor duration.
Sf=C,Sn=max⁡(C,Fa)S_f=C,\qquad S_n=\max(C,F_a)Sf​=C,Sn​=max(C,Fa​)Sf=C,Sn=max⁡(C,Fa)\begin{gathered}S_f=C, \\ S_n=\max(C,F_a)\end{gathered}Sf​=C,Sn​=max(C,Fa​)​
where SfS_fSf​ is the fixed successor start, CCC the constraint date, SnS_nSn​ the not earlier than successor start, and FaF_aFa​ actual predecessor finish.
Ef=Sf+ds,En=Sn+dsE_f=S_f+d_s,\qquad E_n=S_n+d_sEf​=Sf​+ds​,En​=Sn​+ds​Ef=Sf+ds,En=Sn+ds\begin{gathered}E_f=S_f+d_s, \\ E_n=S_n+d_s\end{gathered}Ef​=Sf​+ds​,En​=Sn​+ds​​
where EfE_fEf​ is fixed completion, dsd_sds​ successor duration, and EnE_nEn​ not earlier than completion.

A worked example

Foundation starts on 2026-01-01 and lasts 10 whole days, so its planned finish boundary is 2026-01-11.

Its actual finish on 2026-02-06 is 26 days late. The Frame constraint date is 2026-01-20, leaving an original gap of 9 days.

With fixed start, Frame still runs from 2026-01-20 to 2026-01-25. All 26 delay days stop, zero reach completion, and 17 days overlap without support from the typed sequence.

With not earlier than, 9 days are absorbed and 17 reach completion. Frame runs from 2026-02-06 to 2026-02-11, which is 1 day beyond the typed target.

How the two float readings are formed

Under fixed start, predecessor total float is the constraint date minus predecessor finish, while successor total float is the typed target minus model completion. Under not earlier than, both use the target derived late successor start. A negative number names an overlap against the relationship date or a miss against the typed target, as stated beside it. It does not assign fault.
ϕp,f=C−Fa,ϕs,f=T−Ef\phi_{p,f}=C-F_a,\qquad \phi_{s,f}=T-E_fϕp,f​=C−Fa​,ϕs,f​=T−Ef​ϕp,f=C−Fa,ϕs,f=T−Ef\begin{gathered}\phi_{p,f}=C-F_a, \\ \phi_{s,f}=T-E_f\end{gathered}ϕp,f​=C−Fa​,ϕs,f​=T−Ef​​
where ϕp,f\phi_{p,f}ϕp,f​ is predecessor float under fixed start, ϕs,f\phi_{s,f}ϕs,f​ successor float under fixed start, and TTT the typed target.
L=T−ds,ϕp,n=L−Fa,ϕs,n=L−SnL=T-d_s,\qquad \phi_{p,n}=L-F_a,\qquad \phi_{s,n}=L-S_nL=T−ds​,ϕp,n​=L−Fa​,ϕs,n​=L−Sn​L=T−ds,ϕp,n=L−Fa,ϕs,n=L−Sn\begin{gathered}L=T-d_s, \\ \phi_{p,n}=L-F_a, \\ \phi_{s,n}=L-S_n\end{gathered}L=T−ds​,ϕp,n​=L−Fa​,ϕs,n​=L−Sn​​
where LLL is the late successor start, ϕp,n\phi_{p,n}ϕp,n​ predecessor float under not earlier than, and ϕs,n\phi_{s,n}ϕs,n​ successor float under not earlier than.

What this does not model

It does not decide whether the date constraint is proper, whether the apparent overlap can be worked, who carries delay, whether time or money follows, or what a schedule specification requires.

What the sweep moves

Only actual predecessor finish moves. Every civil date in the typed inclusive range is evaluated without sampling. Activity names, durations, relationship, constraint date, target and selected reading hold fixed.

Permanent refusal

Responsibility, entitlement, compensability, overlap feasibility and schedule compliance are outside the exact input contract. A field asking for any of them is refused rather than ignored.

The calculation domain

The chain contains one finish to start relationship, durations from 1 to 366 whole days, possible Gregorian dates in YYYY MM DD form, and an inclusive sweep spanning no more than 366 days.

Boundary

This reads the dates, durations, target, and finish to start relationship typed by the visitor. It does not decide whether a date constraint is proper, whether an overlap could be worked, who carries delay, whether time or money follows, or what any schedule specification requires.

Source anchors

  • Oracle Primavera Cloud documentation, activity constraints and relationship logic.
  • Society of Construction Law, Delay and Disruption Protocol, second edition, 2017.

The sources are cited for the distinction between calculated sequence logic and imposed dates. No source definition, table or method is reproduced. The civil date arithmetic is stated independently on this page.

Calculation version

1.0.0

The whole record prints. Your browser can save it as a PDF instead of printing it.

Oracle scheduling documentation and the Society of Construction Law Delay and Disruption Protocol are cited by structure and not reproduced. Responsibility, entitlement, compensability, overlap feasibility and schedule compliance are permanently outside this page. Its two readings describe only the typed chain and do not determine whether either setting is proper for a real programme.

Related

  • Total float: who owns it decides whether the finish date movesA supplier runs 20 days late into an activity with 25 days of float and the finish date does not move. The second time it does, and the reason is something that happened weeks earlier to somebody else.
  • Schedule update analysis: the update moved six days, the calculation forty twoThe last programme forecast completion on 16 March and the new one forecasts 10 March, so the two issued programmes sit six days apart. Recorded progress on its own moved the date eighteen days later, and the revisions moved it twenty four days the other way. Forty two days of movement, six days of it visible, and the calculation that sits between the two programmes is the only place the difference shows.

Fixed date chain record

Date constraint: the delay in front of the date stopped travelling

Accepted inputs

Predecessor, Activity name
Foundation
Planned predecessor start
2026-01-01
Predecessor, Duration
10 days
Successor, Activity name
Frame
Successor, Duration
5 days
Actual predecessor finish
2026-02-06
Relationship
Finish to start
Successor constraint date
2026-01-20
Typed completion target
2026-02-10
Tracked date reading
Fixed start
First actual finish date
2026-01-05
Last actual finish date
2026-02-10

All results

fixed start, Successor start
2026-01-20
fixed start, Completion
2026-01-25
fixed start, Completion movement
0 days
fixed start, Delay not reaching completion
26 days
fixed start, Delay reaching completion
0 days
fixed start, Unsupported overlap
17 days
fixed start, Predecessor total float
−17 days
fixed start, Successor total float
16 days
not earlier than, Successor start
2026-02-06
not earlier than, Completion
2026-02-11
not earlier than, Completion movement
17 days
not earlier than, Delay not reaching completion
9 days
not earlier than, Delay reaching completion
17 days
not earlier than, Unsupported overlap
0 days
not earlier than, Predecessor total float
−1 day
not earlier than, Successor total float
−1 day
First tracked change below
2026-02-05
First tracked change above
2026-02-07

Record fields

Calculation version
1.0.0
Boundary
This reads the dates, durations, target, and finish to start relationship typed by the visitor. It does not decide whether a date constraint is proper, whether an overlap could be worked, who carries delay, whether time or money follows, or what any schedule specification requires.
Calculation trace
Treat every date as an exclusive civil day boundary. Planned predecessor finish is planned start plus predecessor duration. Fixed start always places the successor on the constraint date. Not earlier than places it on the later of the constraint date and predecessor finish. Successor completion is its resulting start plus its duration.
Fp=Sp+dpF_p=S_p+d_pFp​=Sp​+dp​
where FpF_pFp​ is planned predecessor finish, SpS_pSp​ planned predecessor start, and dpd_pdp​ predecessor duration.
Sf=C,Sn=max⁡(C,Fa)S_f=C,\qquad S_n=\max(C,F_a)Sf​=C,Sn​=max(C,Fa​)Sf=C,Sn=max⁡(C,Fa)\begin{gathered}S_f=C, \\ S_n=\max(C,F_a)\end{gathered}Sf​=C,Sn​=max(C,Fa​)​
where SfS_fSf​ is the fixed successor start, CCC the constraint date, SnS_nSn​ the not earlier than successor start, and FaF_aFa​ actual predecessor finish.
Ef=Sf+ds,En=Sn+dsE_f=S_f+d_s,\qquad E_n=S_n+d_sEf​=Sf​+ds​,En​=Sn​+ds​Ef=Sf+ds,En=Sn+ds\begin{gathered}E_f=S_f+d_s, \\ E_n=S_n+d_s\end{gathered}Ef​=Sf​+ds​,En​=Sn​+ds​​
where EfE_fEf​ is fixed completion, dsd_sds​ successor duration, and EnE_nEn​ not earlier than completion. Only actual predecessor finish moves. Every civil date in the typed inclusive range is evaluated without sampling. Activity names, durations, relationship, constraint date, target and selected reading hold fixed.
Source anchors
Oracle Primavera Cloud documentation, activity constraints and relationship logic. Society of Construction Law, Delay and Disruption Protocol, second edition, 2017.

Oracle scheduling documentation and the Society of Construction Law Delay and Disruption Protocol are cited by structure and not reproduced. Responsibility, entitlement, compensability, overlap feasibility and schedule compliance are permanently outside this page. Its two readings describe only the typed chain and do not determine whether either setting is proper for a real programme.