Fixed date chain record
Date constraint: the delay in front of the date stopped travelling
Accepted inputs
- Predecessor, Activity name
- Foundation
- Planned predecessor start
- 2026-01-01
- Predecessor, Duration
- 10 days
- Successor, Activity name
- Frame
- Successor, Duration
- 5 days
- Actual predecessor finish
- 2026-02-06
- Relationship
- Finish to start
- Successor constraint date
- 2026-01-20
- Typed completion target
- 2026-02-10
- Tracked date reading
- Fixed start
- First actual finish date
- 2026-01-05
- Last actual finish date
- 2026-02-10
All results
- fixed start, Successor start
- 2026-01-20
- fixed start, Completion
- 2026-01-25
- fixed start, Completion movement
- 0 days
- fixed start, Delay not reaching completion
- 26 days
- fixed start, Delay reaching completion
- 0 days
- fixed start, Unsupported overlap
- 17 days
- fixed start, Predecessor total float
- −17 days
- fixed start, Successor total float
- 16 days
- not earlier than, Successor start
- 2026-02-06
- not earlier than, Completion
- 2026-02-11
- not earlier than, Completion movement
- 17 days
- not earlier than, Delay not reaching completion
- 9 days
- not earlier than, Delay reaching completion
- 17 days
- not earlier than, Unsupported overlap
- 0 days
- not earlier than, Predecessor total float
- −1 day
- not earlier than, Successor total float
- −1 day
- First tracked change below
- 2026-02-05
- First tracked change above
- 2026-02-07
Record fields
- Calculation version
- 1.0.0
- Boundary
- This reads the dates, durations, target, and finish to start relationship typed by the visitor. It does not decide whether a date constraint is proper, whether an overlap could be worked, who carries delay, whether time or money follows, or what any schedule specification requires.
- Calculation trace
- Treat every date as an exclusive civil day boundary. Planned predecessor finish is planned start plus predecessor duration. Fixed start always places the successor on the constraint date. Not earlier than places it on the later of the constraint date and predecessor finish. Successor completion is its resulting start plus its duration.where is planned predecessor finish, planned predecessor start, and predecessor duration.where is the fixed successor start, the constraint date, the not earlier than successor start, and actual predecessor finish.where is fixed completion, successor duration, and not earlier than completion. Only actual predecessor finish moves. Every civil date in the typed inclusive range is evaluated without sampling. Activity names, durations, relationship, constraint date, target and selected reading hold fixed.
- Source anchors
- Oracle Primavera Cloud documentation, activity constraints and relationship logic. Society of Construction Law, Delay and Disruption Protocol, second edition, 2017.