Transfer lots: the next station starts before this one finishes
Split one batch into transfer lots and the next station starts before this one finishes. The overlap is real time back, and it has a price the schedule never shows.
Your prediction before the experiment
The schedule held still
- Total quantity
- 100 units
- Stage one
- 10 s setup, then 1 s per unit
- Stage two
- 5 s setup, then 1.5 s per unit
- Order
- Two serial stages, transfer lots processed in order
- Excluded
- No transport time, blocking, variability, or lot dependent setup
The one change
Enter a whole number from 10 through 100.
Open the recurrence
How the ledger advances
Each row waits for two facts: its upstream completion and the previous downstream completion. The later of those becomes the downstream start. Its own downstream processing time is then added.
where is the upstream completion of a transfer lot, the upstream start, the units released up to that lot, the upstream time a unit, the downstream start, the downstream completion, the units in the lot, and the downstream time a unit.
Worked example
With 20 unit transfer lots, stage one releases at 30, 50, 70, 90, and 110 seconds. Stage two finishes those lots at 60, 90, 120, 150, and 180 seconds. The unsplit batch finishes at 260 seconds. The processing work itself, setup and run time together, stays the same in both cases and is not the completion time, in seconds:
Across the whole admitted range the finish time is 160 seconds plus the transfer lot size, so every ten units removed from the lot returns ten seconds.
where is the finish time in seconds and the transfer lot size in units.
This model does not optimize a transfer lot, promise completion, infer capacity, recommend staffing or sequencing, represent variability, or establish production, quality, commercial, or safety adequacy.