Concurrent delay: two delays at once, five different answers
An employer delay and a contractor delay land on the same three weeks. The facts do not change and neither do the dates, but every analysis method awards a different number of days.
- Days both sides were delaying25 days
- Impacted as planned30 days
- Time impact analysis30 days
- As planned against as built17.5 days
- Collapsed as built5 days
- Windows5 days
The two delays
Try a scenario
Contractor delay
Employer delay
- They overlap for
- 25 days
The numbers below are what five methods do to one deliberately simple pair of delays. They do not decide entitlement and are not evidence for a real programme or contract.
What actually happened
| Days only the contractor was delaying | 5 |
|---|---|
| Days only the employer was delaying | 5 |
| Days both were | 25 |
| Days late in total | 35 |
What each method awards
Impacted as planned
Insert the employer delay into the baseline and measure the movement without considering the contractor delay.
- Baseline finish
- day 75
- Insert the employer delay
- 30 days
- Projected movement
- 30 days
Time impact analysis
Insert the employer event into the programme as it stood when that event began and measure the projected movement.
- Programme when the employer event begins
- day 25
- Insert the employer event
- 30 days
- Projected completion movement
- 30 days
As planned against as built
Give the employer-only days in full and share the concurrent days evenly.
- Employer only days
- 5 days
- Concurrent days, shared evenly
- 12.5 days
- Award
- 17.5 days
Collapsed as built
Remove the employer delay from the as-built record and measure the time saved.
- As built finish
- day 110
- Remove the employer delay, contractor delay alone
- day 105
- The difference
- 5 days
Windows
Split the overrun at every event boundary, give employer-only windows, and give concurrent windows to neither side.
- Employer only windows
- 5 days
- Concurrent windows, awarded to neither
- 25 days
- Award
- 5 days
Why the method is a choice
None of these five methods is wrong. Each answers a slightly different question: what the employer's delay would have done to the plan, what it did to the programme on the day, what the record shows the two of them did between them, and what would have happened without one of them.
The uncomfortable part is that the method is usually chosen after the outcome is known, by whichever side benefits from it, and then defended as though it had been the obvious one all along. A claim that does not name its method, say why that method suits these facts, and show the working is asking to be rejected, and it usually is.
The version above is deliberately simple: one chain, two events, no movement of the critical path. Real programmes have hundreds of activities and a critical path that changes hands several times, which makes the gap between these five numbers wider rather than narrower.
Here is the maths
The duration comparison holds overlap at 10 days, rework at 25%, extra crews at 2, each at 60% efficiency, and available crews at 2.
- Model version
- 1.0
The formula, in words
- The baseline is a three activity chain. It starts on day 0 and finishes on day 75 under the shared critical path engine.
- A delay window includes its start and excludes its end. The overlap is the part inside both windows. The total overrun is both window lengths with that overlap counted once. where is the total overrun, the employer window, the contractor window, and their overlap.
- Employer only days are the employer's window minus the overlap. Contractor only days are the contractor's window minus the overlap. The actual finish is day 75 plus the total overrun. where is employer only days, contractor only days, and the actual finish day.
- Impacted as planned and time impact analysis each award the employer's full window here. On this single chain, neither looks at what the contractor was doing, so they agree.
- As planned against as built adds the employer only days to half the overlap. Collapsed as built and windows each award the employer only days under the single rules used on this page. where is the award from sharing the overlap equally.
- When the events do not overlap, every method awards the employer's full delay. When they overlap, the difference between the longest and shortest award is exactly the length of that overlap.
- These rules stand in for five families of practice. Variants inside each family also disagree. The method is part of the analysis, not a neutral wrapper around it.
- A duration is elapsed time, and a finish is the moment the work ends. An activity of five days starting at day 0 finishes at day 5, not day 4. A finish to start successor starts at day 5.
- This is the continuous convention rather than the inclusive day convention. It is chosen because every off by one error in a hand check of a critical path comes from the other one, and because both lesson pages ask readers to check the arithmetic themselves.
- Overlap gains the days brought forward and gives back the share that must be redone. Adding crews divides the 40 day construction activity by one plus the effective extra crew contribution. Its crew time is the crews used over the shorter window minus the original 40 crew days. where is rework days, days brought forward, the rework fraction, and the net gain.where is the shortened construction duration, extra crews, each extra crew’s efficiency, and extra crew days.
- Durations are elapsed working days and every day counts. There is no calendar, no date and no imposed completion date.
A worked example
Impacted as planned takes the employer's 30 day delay, drops it into the original programme and reports 30 days. It never looks at the contractor at all.
Same programme. Same two delays. Same 35 days late. Thirty days, five days, or seventeen and a half, depending on which of these you open with.
What this does not model
A moving critical path, which is where real analyses diverge most; float and whether either delay consumed it; mitigation and acceleration beyond the two resource sketches shown here; notice, and whether it was given in time; the contract form, which decides more of this than the arithmetic does; money cost, prolongation, disruption and damages of any kind; whether either delay actually affected critical work, which is what most real disputes are about; and the variants inside each of these five method families, which disagree with each other as much as the families disagree.
Check it yourself
Enter day 55 as the start of the employer's delay. It no longer overlaps the contractor's, and all five methods award 30 days. Every difference on this page is the overlap and nothing else.
Two ways to buy the same days
same 75 day baselineOverlapping 10 days of testing into construction gains 7.5 days once 2.5 days of rework is taken back, at 2.5 crew days of crew time. Adding 2 crews gains 21.82 days at 14.55 crew days of crew time, and creates no rework.
That profile asks for 3 crews for 18.2 days, against the 2 in the fixed example. The bar chart above does not know that, which is why this one is here.
It is not a delay analysis or an entitlement calculation. Each method here is a single stated rule standing in for a whole family of practices, real programmes have a critical path that moves and this one does not, and the question of which method suits a given set of facts is a matter for the contract and for a delay analyst. No number here belongs in a notice or a claim.