Logic links: one side's delay disappeared, the other kept all of it

A first delay pushes completion by 5 days. Then a second delay of 20 days lands on the same activity, and whoever holds the sequence changes two downstream links from finish to start into start to start. Predict how far completion moves the second time, then watch it move 20 days, 10, or none at all as the count of changed links runs from 0 to 2. The 20 days are still sitting in the activity, and a reading that looks only at the finish date cannot see them.

Your prediction before the experiment

A longer second delay on the same activity moves completion by that longer delay. The first delay has already moved completion by 5 days. Predict the next movement, then change the downstream link.
A longer second delay on the same activity moves completion by that longer delay. The first delay has already moved completion by 5 days. Predict the next movement, then change the downstream link.

What stays fixed

Precondition
The same activity scope and information in every reading
Activities
Excavate, Support, Pour
Base durations
10 days each
First delay
5 days on Excavate
Second delay
20 more days on Excavate
Reference
Both original links after the first delay

The relationship reading

Changed downstream links

One changes Support to Pour first. Two then changes Excavate to Support. The order never changes.

Three relationship readings of the same delayed activityThree aligned network strips keep the same activities and delays. With zero, one, and two changed links, incremental completion movement is 20, 10, 0 days. The selected reading changes 0 links and the delayed first activity still lasts 35 days.Activity periodsMove the relationshipcontrol to reveal thethree readings.01020304055Completion

This recalculates the typed three activity network after the exact link changes shown here. It assigns no responsibility, judges no relationship, decides no entitlement, and takes no view on which links in real work are physical.

Here is the maths

▾

The formula, in words

The reference completion uses the first delay and both original finish to start links. The current completion uses both delays and the selected changes. The latest finish among all three current activities is retained, then the reference completion is subtracted.

ΔC=Cc−Cr\Delta C=C_c-C_rΔC=Cc​−Cr​

where ΔC\Delta CΔC is incremental movement, CcC_cCc​ the latest current finish, and CrC_rCr​ the reference completion after the first delay.

A worked example

  1. The three base durations are 10 days. After the first 5 day delay, the reference completion is 35.
  2. The second delay makes the first activity last 35 days. With both original links, completion is 55 and movement is 20.
  3. Change Support to Pour and completion is 45, so movement is 10. Change Excavate to Support as well and the latest finish is 35, so movement is 0.
15+10+10=35,35+10+10=55,55−35=2015 + 10 + 10 = 35,\qquad 35 + 10 + 10 = 55,\qquad 55 - 35 = 2015+10+10=35,35+10+10=55,55−35=2015+10+10=35,35+10+10=55,55−35=20\begin{gathered}15 + 10 + 10 = 35, \\ 35 + 10 + 10 = 55, \\ 55 - 35 = 20\end{gathered}15+10+10=35,35+10+10=55,55−35=20​

What this does not model

The calculation accepts exactly three named activities and exactly two downstream relationship positions. It does not decide who controls a relationship, whether a relationship is reasonable, or whether the resulting overlap can occur in real work.

Source basis

Published scheduling mathematics and delay analysis guidance supply structural context for chosen sequence logic, date effective correction, and visible relationship change records. The lesson reproduces no source wording and teaches no generic path switch or revision trace.

This lesson does not assign a relationship to a party or classify one as justified, compensable, compliant, or physically necessary. Fields asking for those conclusions are refused rather than ignored.

Related

  • Concurrent delay: two delays at once, five different answersAn employer delay and a contractor delay land on the same three weeks. The facts do not change and neither do the dates, but every analysis method awards a different number of days.Interactive lesson · 4 min
  • Schedule update analysis: the update moved six days, the calculation forty twoThe last programme forecast completion on 16 March and the new one forecasts 10 March, so the two issued programmes sit six days apart. Recorded progress on its own moved the date eighteen days later, and the revisions moved it twenty four days the other way. Forty two days of movement, six days of it visible, and the calculation that sits between the two programmes is the only place the difference shows.Interactive lesson · 4 min