Last safe approval record
Approval lead time: the change is one delay, the answer another
Accepted inputs
- Proposal date
- 2026-04-01
- Approval date
- 2026-04-14
- Change effect held separately
- 11 days
- Dependency 1
- Design release, 7 days, 2026-04-17
- Dependency 2
- Order amendment, 5 days, 2026-04-20
- Dependency 3
- Vendor queue, 10 days, 2026-04-26
- Dependency 4
- Material commitment, 6 days, 2026-04-24
- Dependency 5
- Work opening, 2 days, 2026-05-01, 2026-05-08, 2026-05-15, 2026-05-22, 2026-05-29, 2026-06-05, 2026-06-12
Tracked answer
- Last safe approval
- 2026-04-10
- Binding dependency
- Design release
- Added waiting days
- 4 days
- Change effect days
- 11 days, held separately
Record fields
- Calculation version
- 1.0.0
- Boundary
- It walks the leads and civil dates you typed, keeps change effect separate from approval deferral, and does not price a change, decide entitlement, judge reasonableness, or read an agreement.
- Source
- U.S. Government Accountability Office, Schedule Assessment Guide