Duplicate resource intersection record
Double counting: one crew, and the same hours in the total twice
Accepted inputs
- Claim line 1, Line ID
- variation
- Claim line 1, Claim label
- Typed line A
- Claim line 1, Resource label
- Site crew
- Claim line 1, Event label
- Change 01
- Claim line 1, Valuation route label
- Variation rate
- Claim line 1, First week
- 10
- Claim line 1, Last week
- 13
- Claim line 1, Weekly line amount
- 100,000 cost units
- Claim line 1, Included resource share
- 20 percent
- Claim line 2, Line ID
- time_line
- Claim line 2, Claim label
- Typed line B
- Claim line 2, Resource label
- Site crew
- Claim line 2, Event label
- Change 01
- Claim line 2, Valuation route label
- Time based line
- Claim line 2, First week
- 10
- Claim line 2, Last week
- 13
- Claim line 2, Weekly line amount
- 20,000 cost units
- Claim line 2, Included resource share
- 100 percent
- Claim line 3, Line ID
- extra_staff
- Claim line 3, Claim label
- Typed line C
- Claim line 3, Resource label
- Additional crew
- Claim line 3, Event label
- Change 01
- Claim line 3, Valuation route label
- Staffing line
- Claim line 3, First week
- 10
- Claim line 3, Last week
- 13
- Claim line 3, Weekly line amount
- 10,000 cost units
- Claim line 3, Included resource share
- 100 percent
All results
- Whole duplicate amount
- 80,000 cost units
- Named pairs
- 1
- Duplicated weekly triples
- 4
- Deduction route
- none chosen
Sweep of Included resource share on the first line
- The assumption
- Included resource share on the first line
- Values sampled
- 0 to 40, 5
- The answer
- 80,000
- Holds across
- 20 to 40
- Nearest change
- 10, 40,000
- Reading the boundary
- The sweep samples only the values you entered. Between samples the answer is not checked, so read the boundary as observed, not proven.
Record fields
- Calculation version
- 1.0.0
- Boundary
- It intersects visitor labelled lines under a stated same scope and same information assumption, prices nothing, chooses no deduction route, and makes no finding about entitlement, compensability, accuracy or overstatement.
- Calculation trace
- For each resource, event and whole week, group the covered amount by valuation route. Add the route amounts, subtract the largest route amount, and then add those weekly excess amounts. Candidate pairs are named separately and are never added to form the total. Only the first line's declared included percentage changes. Every label, week, weekly amount and other share holds fixed. In the worked record the total grows to 80,000 at 20 percent and stays there because the second route carries only 20,000 a week.
- Source anchors
- Society of Construction Law, Delay and Disruption Protocol, second edition, 2017. AACE International, Recommended Practice 29R 03, Forensic Schedule Analysis.