Prolongation and disruption: delay costs money twice
Staying on site longer is one cost. Working less efficiently while you are there is a different one, proved with different records, and pricing either of them in the wrong month moves the figure further than the delay did.
- weeks pricedSix weeks
- difference between the two windows$55,742
This page illustrates two methods on synthetic facts. The figures are not added together, and neither measures productivity loss, which needs different records. The page does not assess a claim, decide compensability, award time, or calculate a sum due, owed, recoverable or claimable. It accepts no project facts: there are no fields for a contract value, completion date, rate or claim.
The first frame is one works programme over ten months, planned to finish at the end of October and finishing on 12 December, six weeks late, with an employer event landing at the start of September.
Price the period
Try a scenario
Limit: 8 weeks because the fixed cost record ends in December.
That trade's standing cost, outside the programme period cost above.
The fixed monthly cost record
| Mar | 38,000 |
|---|---|
| Apr | 72,000 |
| May | 126,000 |
| Jun | 150,000 |
| Jul | 150,000 |
| Aug | 138,000 |
| Sep | 102,000 |
| Oct | 66,000 |
| Nov | 54,000 |
| Dec | 46,000 |
| Mar | Apr | May | Jun | Jul |
|---|---|---|---|---|
| 38,000 | 72,000 | 126,000 | 150,000 | 150,000 |
| Aug | Sep | Oct | Nov | Dec |
| 138,000 | 102,000 | 66,000 | 54,000 | 46,000 |
The programme does not spend at one rate. These ten monthly figures are asserted for the synthetic scenario.
Compare the crew with itself
A repetitive install covers 2,400 units of unchanged work. The same crew completed 1,800 units in 900 unimpacted hours, or 2.00 units an hour. The tender allowed 2.50 units an hour. Labour is $58 an hour all in.
| Six weeks, priced where the delay took effect | $127,548 |
|---|---|
| Six weeks, priced in the overrun window | $71,806 |
| Difference | $55,742 |
| Hours the event cost | 400, or $23,200 |
| Hours against the tender | 640, or $37,120 |
| The difference between those two | 240, or $13,920 |
Where the money actually was
Two questions, four cells
The affected work was
Cost during the period is
Both questions are open
The time question would require records showing that the event moved completion. The money question would separately require time-related cost records from the period the delay took effect, with the cost separated from your own delay. This cell establishes neither point by itself.
Hours for the same work
Four costs, and who is standing under each
nothing here is added to anything else- Waiting on site
- On this scenario$127,548.39Who is standing under itWhoever the contract puts the period onWhich clockContractual, priced by the month it fell in
- A following trade blocked
- On this scenario$13,800.00Who is standing under itThe blocked party, until the contract moves itWhich clockContractual, and it can run inside the same weeks
- Crew present and not producing
- On this scenario$23,200.00Who is standing under itThe party carrying the labourWhich clockPhysical, measured against the crew's own rate
- Restarting after each stoppage
- On this scenarioInside the figure aboveWho is standing under itThe same partyWhich clockNot separable on these records
None of these four is added to another on this page. The first two are read off a contractual clock, which starts when the contract says it starts and not when the work stopped. The third is read off a physical clock, which starts when the crew arrives. The fourth is inside the third on these records, and separating it would need a record of every stoppage, which is the record nobody keeps.
The two questions
They are asked separately because they are answered separately. asks how long time-related resources were held and, just as importantly, when: the level of staff, plant and facilities on a project changes month by month, so a delay in March that pushes the finish into November is not priced by taking November's costs. Disruption asks something else entirely, which is how much less efficiently work was performed while an event was operating, on work that was not itself changed. That last clause is doing more than it looks: changed work is valued through its own route, and the ripple onto the remaining original work is the disruption question.
An event can move the finish date and cost nothing separable, or cost money and move no date at all, or do both, or neither. That is why the grid above has four cells rather than a switch, and why a granted extension is not a figure. It is also why the evidence differs: prolongation is proved from cost records for a period, classified by whether each cost actually moved with time, and disruption is proved from records of what was produced and by whom, made while it was happening rather than reconstructed afterwards.
The two measurements, in words
- Model version
- 1.0
The two measurements, in words
- Prolongation is a period, not a multiplication. The question is which resources were held longer and when, so it is taken from the cost records of the period the delay took effect; multiplying every monthly cost line by the length of the extension is the error the whole page is about.
- Disruption is a rate, not a total. Compare what was produced per hour on affected work against comparable unaffected work, convert the difference to hours, and price the hours.
- The comparison must be with the same crew, not with the tender. A tender is an estimate, and the gap between an estimate and what a crew ever achieved is not something an event caused.
- The two never merge. The same hour cannot sit in both, and where a rate for changed work already carries supervision or overhead, that content is already recovered once.
A worked example
Prolongation, and the month it is taken from. Daily rates come from the month, so September runs at a day and November at . Six weeks is 42 days. Where the delay took effect, from 1 September: 30 days of September at $3,400 is $102,000, plus 12 days of October at is $25,548.39, so $127,548.39. In the overrun window, from 1 November: 30 days of November at $1,800 is $54,000, plus 12 days of December at is $17,806.45, so $71,806.45. The same six weeks, $55,741.94 apart, a factor of 1.78, and nothing about the delay changed between the two lines.
| Event lands | Delay-effect window | Against the overrun window |
|---|---|---|
| March | Delay-effect window$64,400 | Against the overrun window$7,406 less |
| June | Delay-effect window$208,065 | Against the overrun window$136,258 more, a factor of 2.90 |
| September | Delay-effect window$127,548 | Against the overrun window$55,742 more, a factor of 1.78 |
March is the row that stops this being an argument for one method: on a slow start the overrun window overstates. The point is not that one window is bigger, it is that the two differ and the difference is decided by when the programme was spending.
Disruption, and the comparison that is not a method. 2,400 units of unchanged work. The crew's own unimpacted rate, 1,800 units in 900 hours, is 2.00 an hour, so it should have taken 1,200 hours. It took 1,600, a 25% fall in output rate and a 33.3% rise in hours, the two ways of saying it that do not sound like the same number. Against the crew's own rate: hours, at $58, $23,200. Against the tender's 2.50 an hour, which allowed hours: hours, $37,120. The difference is 240 hours, $13,920, and it is not disruption. It is the distance between what was tendered and what this crew ever achieved on a good day, and it belongs where it fell.
The measured comparison goes to zero, correctly, because nothing was lost. The tender comparison still reads $13,920. The gap remains 240 hours: a method that reports a loss when there was no event is not measuring the event.
Where the method descriptions come from
The method descriptions are paraphrased from the Society of Construction Law Delay and Disruption Protocol, AACE International practitioner guidance, and secondary practitioner commentary summarised for this lesson. They are not quotations. Several source positions are one author's argument rather than settled practice, and the page does not present the measured mile and direct time-lost records as a complete list of methods.
What this does not model
Entitlement of any kind, notice, contractual routes, concurrency between named events, float ownership, acceleration, escalation, head-office overhead and its formulae, the comparability tests a real measured mile has to pass, the exclusion of competing causes, and every question about whose delay it was, which is the one this page most deliberately never asks.
The method descriptions paraphrase the Society of Construction Law Delay and Disruption Protocol, AACE International practitioner guidance and secondary practitioner commentary. They do not reproduce source wording, and some positions are one author's argument rather than settled practice.