Time and money: an event passes one gate and fails the other

Type each event with the dates it moved completion on and the dates it held resources on, and say how much float stood in front of it. Two whole day counts come back that are usually different numbers, and every event lands in one of four boxes with the gate it did not pass named beside it. The two counts are never added, because they are read off different records. Nothing here decides entitlement or calls any day compensable.

Live result

The completion date gate returns 3 days, while the resource gate returns 3 days. They stay separate because they come from different typed records.
The completion date gate returns 3 days, while the resource gate returns 3 days. They stay separate because they come from different typed records.

The two typed gates

Where each event sits on the two typed gatesThe chart places 4 events by two yes or no readings. E1 is time only. E2 is money only. E3 is both. E4 is neither. The two union counts are 3 completion effect days and 3 resource effect days.no resource datesresource datescompletion dates remainno completion date remainsE1E2E3E4

Try a scenario

Same event scope and information cut

Both date lists need to describe the same event scope and the same information cut.

0 days
2

Zero absorbs no completion date. A positive whole count absorbs that many earliest typed completion dates.

Event inputs▾

Use YYYY-MM-DD in increasing order, separated by commas. Nothing is inferred between dates.

Event 1

Event 2

day

Zero absorbs no completion date. A positive whole count absorbs that many earliest typed completion dates.

Event 3

days

Zero absorbs no completion date. A positive whole count absorbs that many earliest typed completion dates.

Event 4

days

Zero absorbs no completion date. A positive whole count absorbs that many earliest typed completion dates.

This page shows from 1 to 8 events so every event remains legible in the chart. The calculation accepts up to 50.

Typed float for the first event

days
days
days
days

It does not check the values in between.

How the answer sits across the values sampledA rail of the 5 values sampled, from 0 days to 4 days in steps of 1 day. No other integer in the range leaves the two counts and the first event box at 3 / 3 / Completion dates only. Every admissible integer in this range was checked.first change1 day0 dayson the page

No other integer in the range leaves the two counts and the first event box at 3 / 3 / Completion dates only. Every admissible integer in this range was checked.

No other integer in the range leaves the two counts and the first event box at 3 / 3 / Completion dates only. Every admissible integer in this range was checked.
The answer3 / 3 / Completion dates only
Values sampled0 days to 4 days, 5 values, step 1 day
Holds from0 days, lowest sampled
Holds to0 days
Nearest value that changes it1 day
The answer there2 / 3 / Completion dates only

What an unchanged region does and does not prove is set out in a short lesson.

Every admissible integer in this range was checked. Values outside the range remain unchecked.

First checked change in a count or the target box
At 1 days of typed float · Completion dates only
First checked target box change
At 2 days of typed float · Neither typed list passes

Two counts, kept apart

Distinct completion effect dates after float

3 days

Distinct resource effect dates

3 days

No combined total is produced.

Every event on the two gates

E1

Completion dates only

earliest completion dates absorbed
0
Gate not passed
typed resource gate

E2

Resource dates only

earliest completion dates absorbed
1
Gate not passed
completion date gate

E3

Both typed lists pass

earliest completion dates absorbed
0
Gate not passed
Both gates passed

E4

Neither typed list passes

earliest completion dates absorbed
0
Gate not passed
completion date gate and typed resource gate
Shared completion dates
none
Shared resource dates
none

Boundary

It counts the two typed date sets and places events on two declared gates, without deciding entitlement, classifying compensability, pricing delay, assigning cause, or reading a contract.

Here is the maths

▾

The formula, in words

For each event, sort the typed completion effect dates and absorb the first whole number named by its float. Any remaining completion date passes the first gate. Any typed resource effect date passes the second. Count the union of dates separately for each gate, so a date shared by events appears once in that gate's total.

Ne=∣⋃iDi∣N_e = |\bigcup_i D_i|Ne​=∣i⋃​Di​∣
where NeN_eNe​ is the extension day count, iii the event index, and DiD_iDi​ completion dates remaining after float for that event.
Nr=∣⋃iRi∣N_r = |\bigcup_i R_i|Nr​=∣i⋃​Ri​∣
where NrN_rNr​ is the resource day count and RiR_iRi​ typed resource dates for each event.

A worked example

Event E1 leaves 2 completion dates and no resource date. E2 has its 1 completion date absorbed and keeps 2 resource dates. E3 keeps 1 date in each list. E4 has neither. The first union contains 3 dates and the second union also contains 3 dates, but the two threes are never added.

What this does not model

The boxes only describe the typed lists. They do not classify a claim, price a delay, assign cause, interpret negative float, read a contract, or decide entitlement.

Source basis

The mechanism uses public set union and whole number arithmetic. It reproduces no definition, taxonomy or wording from sold guidance.

The whole record prints. Your browser can save it as a PDF instead of printing it.

The two gates do not decide entitlement or classify an event as compensable, and those requests are always refused.

Related

  • Prolongation and disruption: delay costs money twiceStaying on site longer is one cost. Working less efficiently while you are there is a different one, proved with different records, and pricing either of them in the wrong month moves the figure further than the delay did.
  • Total float: who owns it decides whether the finish date movesA supplier runs 20 days late into an activity with 25 days of float and the finish date does not move. The second time it does, and the reason is something that happened weeks earlier to somebody else.

Two gate event record

Time and money: an event passes one gate and fails the other

Accepted inputs

Event 1
E1
Typed float
0 days
Completion effect dates
2026-01-012026-01-02
Resource effect dates
none
Event 2
E2
Typed float
1 day
Completion effect dates
2026-01-03
Resource effect dates
2026-01-032026-01-04
Event 3
E3
Typed float
0 days
Completion effect dates
2026-01-05
Resource effect dates
2026-01-05
Event 4
E4
Typed float
0 days
Completion effect dates
none
Resource effect dates
none

Separate results

Distinct completion effect dates after float
3
Distinct resource effect dates
3
E1
Completion dates only
E2
Resource dates only
E3
Both typed lists pass
E4
Neither typed list passes

Record fields

Calculation version
1.0.0
Boundary
It counts the two typed date sets and places events on two declared gates, without deciding entitlement, classifying compensability, pricing delay, assigning cause, or reading a contract.
Source basis
The mechanism uses public set union and whole number arithmetic. It reproduces no definition, taxonomy or wording from sold guidance.

The two gates do not decide entitlement or classify an event as compensable, and those requests are always refused.