Delay analysis methods: the records carry them, the software does not

Type what your project file actually holds. Five published methods are read against it, and on the worked file the records carry four. No method is chosen and no entitlement decided.

Live result

4 of the 5 declared methods are carried by this record.
  • Updates in the record3 updates
The declared tie rule names Baseline to as built comparison, and that is not advice.
4 of the 5 declared methods are carried by this record.The declared tie rule names Baseline to as built comparison, and that is not advice.

Carried methods as the update count moves

Live chart
Number of carried methods by contemporaneous update countThe line checks update counts from 0 through 24 while every other record matter stays fixed. At 3 updates, 4 of 5 methods are carried. Counts above 12 are shown together because they do not strengthen this audit.0245methods06121824Contemporaneous updatescarriedYour count · 3 · 4Your count · 3 · 4

Try a record

3
Count stops separating
021224

This is the one dominant control. The carried list can first change at 2, and counts above 12 stop separating the methods in this audit.

Question perspective

What the project file contains

Approved baseline available

Baseline logic checked

Updates carry status dates

Sequence as built available

Delay events have dates

Logic changes are recorded

The complete record demand matrix

Baseline to as built comparison
A retrospective question with a checked baseline and a sequence as built.
Carried by these records
Nothing missing
Collapsed as built comparison
A retrospective question with a sequence as built, dated delay events and logic change records.
Carried by these records
Nothing missing
Contemporaneous event insertion
A prospective question with a checked baseline and dated delay events.
Not carried by these records
a prospective question
Periodic update comparison
A retrospective question with a checked baseline, at least 2 dated updates and a sequence as built.
Carried by these records
Nothing missing
Reconstructed as built critical path
A retrospective question with a sequence as built, dated delay events and logic change records.
Carried by these records
Nothing missing
MethodDeclared demandsWhat is missing
Baseline to as built comparisonCarried by these records4Nothing missing
Collapsed as built comparisonCarried by these records4Nothing missing
Contemporaneous event insertionNot carried by these records4a prospective question
Periodic update comparisonCarried by these records6Nothing missing
Reconstructed as built critical pathCarried by these records4Nothing missing

Named by the declared rule

Baseline to as built comparison

Above 12, the count is shown as 12 or more and does not strengthen any method claim in an audit covering 2 years.

The boundary where this stopsIt reports which public practice methods the typed record set can carry, without recommending one, deciding entitlement, pricing delay, assigning cause, or reading a contract.

Contemporaneous update count

It does not check the values in between.

How the answer sits across the values sampledA rail of the 25 values sampled, from 0 to 24 in steps of 1. Across the values sampled, the carried method list and the name returned by the declared tie rule stays 4 carried, Baseline to as built comparison from 2 to 24, the highest value sampled. The nearest value where it changes is 1, where it becomes 3 carried, Baseline to as built comparison.first change13on the page

Across the values sampled, the carried method list and the name returned by the declared tie rule stays 4 carried, Baseline to as built comparison from 2 to 24, the highest value sampled. The nearest value where it changes is 1, where it becomes 3 carried, Baseline to as built comparison.

Across the values sampled, the carried method list and the name returned by the declared tie rule stays 4 carried, Baseline to as built comparison from 2 to 24, the highest value sampled. The nearest value where it changes is 1, where it becomes 3 carried, Baseline to as built comparison.
The answer4 carried, Baseline to as built comparison
Values sampled0 to 24, 25 values, step 1
Holds from2
Holds to24, highest sampled
Nearest value that changes it1
The answer there3 carried, Baseline to as built comparison

What an unchanged region does and does not prove is set out in a short lesson.

Every admissible integer in this range was checked. Values outside the range remain unchecked.

Here is the maths

▾

The formula, in words

For each method, list every declared record demand that the typed file does not meet. A method is carried only when that missing list is empty. Among carried methods, name the one with the fewest declared demands, then use alphabetical order to settle a tie.

A worked example

  1. The file is retrospective and has a checked baseline, 3 status dated updates, a sequence as built, dated delay events and records of logic changes.
  2. The baseline comparison, collapsed comparison, periodic update comparison and reconstructed path are carried, so the count is 4 of 5.
  3. Four carried methods have declared demand counts of 4, 4, 6 and 4. Alphabetical order settles the 3 way tie at 4, so baseline to as built comparison is the name returned.

What this does not model

The matrix is an independently authored record demand check. It does not reproduce a sold protocol, its categories, a selection table or its wording.

A carried row says only that the typed file contains the demands declared here. It says nothing about quality, admissibility, causation or entitlement.

The name returned by the tie rule is not a method choice and not professional judgement.

What the sweep holds fixed

Only the contemporaneous update count moves from 0 through 24. The perspective and the other 6 record facts stay fixed. The first possible periodic comparison change is checked at 2 updates.

Source anchors

These public sources describe approved plans, schedule maintenance, progress records and dated impact information. They provide practice context only, and no selection taxonomy or method table is reproduced.

  • U.S. Government Accountability Office, Schedule Assessment Guide
  • Federal Highway Administration, standard specifications, section 108
  • U.S. Department of Defense, public schedule specification library

The record demand matrix and the tie rule belong to this page.

The whole record prints. Your browser can save it as a PDF instead of printing it.

A request to choose a method or decide entitlement is refused. A carried method is only a result of the record demands declared on this page, and the mechanically named method is not advice, a suitability finding or a contractual conclusion.

Related

  • Concurrent delay: two delays at once, five different answersAn employer delay and a contractor delay land on the same three weeks. The facts do not change and neither do the dates, but every analysis method awards a different number of days.
  • Claim preparation: assemble a packet and hear what a reviewer asksPick the evidence, do the arithmetic, and a reviewer walks the packet naming what is missing, what does not agree with something else in it, and what a real one would ask next. There is no mark at the end, because a reviewer does not give one.

Record support audit

Delay analysis methods: the records carry them, the software does not

Accepted record

Question perspective
Retrospective
Contemporaneous updates
3
What the project file contains
Approved baseline available: Yes, Baseline logic checked: Yes, Updates carry status dates: Yes, Sequence as built available: Yes, Delay events have dates: Yes, Logic changes are recorded: Yes

Results

Methods carried
Baseline to as built comparison, Collapsed as built comparison, Periodic update comparison, Reconstructed as built critical path
Name returned by the declared rule
Baseline to as built comparison
Method row Baseline to as built comparison
Nothing missing
Method row Collapsed as built comparison
Nothing missing
Method row Contemporaneous event insertion
a prospective question
Method row Periodic update comparison
Nothing missing
Method row Reconstructed as built critical path
Nothing missing

Record fields

Calculation version
1.0.0
Boundary
It reports which public practice methods the typed record set can carry, without recommending one, deciding entitlement, pricing delay, assigning cause, or reading a contract.

A request to choose a method or decide entitlement is refused. A carried method is only a result of the record demands declared on this page, and the mechanically named method is not advice, a suitability finding or a contractual conclusion.