Driving delay calculation record
Driving delay: separate events can share a completion effect
Inputs in days
- Fabrication float
- 15
- Contractor event length
- 30
- Employer event start day
- 62
- Employer event length
- 20
- Fixed contractor start day
- 30
Two readings and completion days
- Event-calendar overlap
- 0
- Shared completion effect
- 15
- Combined overrun
- 20
- Planned finish
- 100
- Contractor-only insertion finish
- 115
- Employer-only insertion finish
- 120
- Combined finish
- 120
Numbered receipt
- 1
- Baseline finish 100; contractor-only insertion finish 115; employer-only insertion finish 120.
- 2
- The smaller separate finish is 115; its extension beyond day 100 is 15 days.
- 3
- Shared effect 15, contractor-only tail 0 and employer-only tail 5 total 20 days; combined finish 120.
Source basis
- Source basis
- An authored synthetic network, evaluated by the site's critical path forward and backward passes. Both interval intersections are derived here from their endpoints. The names distinguish the two readings on this page; no published protocol wording or standard table is reproduced.