One more bidder: a fourth supplier does more than the best price ceiling
Three suppliers with costs from 80 to 120 face an alternative at 130. A ceiling of 105 saves 30.40; a fourth supplier without it saves 34.00. At cost 90, another rival trims the bid from 100.00 to 97.50 and the expected margin from 5.63 to 3.16.
- Expected price with no ceiling100.00
- Saving with no ceiling30.00
- Best ceiling105.00
- Saving with the ceiling30.40
- Saving with one more bidder34.00
Givens
- Your seat
- Buyer
Three tenders
Maintenance suppliers estimate the same scope with different labour and subcontract costs.
- Low cost
- 80
Both edges run from 0.01 to 1,000,000,000, in one unit of price.
- High cost
- 120
- Suppliers bidding
- 3
A whole count from 1 to 8, of suppliers who actually bid.
- The alternative price
- 130
Your fallback price if no bid is accepted, above the low cost.
- Costs
- Private to each supplier, independent and spread evenly across the range.
- Award
- The lowest bid wins.
- Bidding
- Every supplier bids as the maths says.
- Without a ceiling
- The buyer accepts any bid up to its alternative price.
One more bidder and the ceiling
This page shows what a mechanism does under stated rules and says nothing about any public procurement regulation. The costs and the alternative are your own estimates. No count, bid or ceiling is recommended.
Every count from 1 to 8
| Count | Expected price | Saving with no ceiling | Saving with the best ceiling | Gain from one more bidder |
|---|---|---|---|---|
| 1 | 130.00 | 0.00 | 15.63 | 23.33 |
| 2 | 106.67 | 23.33 | 24.74 | 6.67 |
| 3typed | 100.00 | 30.00 | 30.40 | 4.00 |
| 4 | 96.00 | 34.00 | 34.12 | 2.67 |
| 5 | 93.33 | 36.67 | 36.70 | 1.90 |
| 6 | 91.43 | 38.57 | 38.58 | 1.43 |
| 7 | 90.00 | 40.00 | 40.00 | 1.11 |
| 8 | 88.89 | 41.11 | 41.11 | 0.89 |
Here is the maths
The mechanism
A ceiling can leave the buyer using its fallback. Another genuine bidder changes the cost competition itself. Expected saving counts both purchases and fallback outcomes.
A worked example
The ceiling changes the chance of buying as well as the payment. The extra supplier increases saving by more than that ceiling does.
- At costs 80 to 120 with three bidders, the expected price is:
- Against the alternative 130, saving is:
- The best ceiling gives saving that rounds to 30.40:
- A fourth bidder without a ceiling gives:
Show the full maths
The costs in order
Why that ceiling
Where the shade comes from
The comparison and its boundary
The comparison needs independent private values and the same distribution for genuine bidders. In this buyer's mirror, the alternative must cover the whole cost range. Inside the range the ceiling can do better, as the live reading shows. The comparison does not price the work of attracting a bidder or predict entry.
A shared unknown value can reverse it
Sources
- Paul Milgrom, Putting Auction Theory to Work
- Paul Klemperer, Auctions: Theory and Practice
- Tim Roughgarden, Twenty Lectures on Algorithmic Game Theory
- Scale
- Whole counts, amounts to 2 decimals with scientific notation for very large amounts, table chances to whole percentages
- Basis
- Independent uniform private costs, genuine bidders and equilibrium bids
- Model version
- 1.0.0
The whole record prints. Your browser can save it as a PDF instead of printing it.
This model reads stated assumptions and your estimates. It does not predict a tender outcome or recommend a bidder count, bid or price ceiling.
Related
- Bid cost: the eighth invitation is the first that loses moneyA bid costs 20,000 to prepare and 150,000 if it wins. One chance in seven still pays 1,429; one in eight loses 1,250. Seven holds and the eighth invitation is the first that loses money. The page names no number to invite.Interactive lesson · 3 min
- Winner's curse: the lowest bid understood the job leastSix contractors price the same scope from the same information and one comes in well below the rest. Predict what happens to the winning bid's distance below true cost as more bidders are invited, then move the count from 2 to 20 and watch it rise. At an estimating spread of 8% the lowest of five bids is expected 9.3% under and the lowest of six is 10.1%, which is the first count past a 10% contingency. No bid is labelled and no number of bidders to invite is named.Interactive lesson · 4 min