Setup load: the fast cycle still falls short

A 60 second run time suggests a station covers 40 units an hour, but setups between batches eat its time. Type the batch and the occupied times, and the real capacity and the break even batch appear.

Capacity after every setup

The station returns 34.3 units/hour, below demand of 40.0, with 1,800 seconds of setup per 40 units and 60 seconds of run work per unit.

Capacity, units/hour

Live chart
Production batch capacity beside hourly demandThe solid capacity curve rises from 1.9 at 1 unit to 46.2 at 100 units. The dashed demand line stays at 40.0 units/hour. The entered batch returns 34.3. The first whole batch above demand is 61. The text table gives the entered batch and the crossing neighbourhood.0.027.254.5150100CapacityDemand

Production batch, units

Entered batch40Equal capacity60
Units
The view runs from 1 to 100 units; the comparison checks every whole batch from 1 to 1,000

Count the workstation time occupied by one setup and every unit in the repeated batch

Setup times, seconds

Where the spare time begins

First whole batch above demand
61 units
Whole batch equal to demand
60 units
Run-only capacity, units/hour
60.0
Required load, percent
116.7
Cycle spent on setup, percent
42.9

An equal capacity leaves zero spare time in this repeated-cycle ledger

Entered batch and crossing neighbourhood
Entered batch and crossing neighbourhood
Batch, unitsCapacity, units/hourReading
4034.3Below demand
5939.8Below demand
6040.0Equal to demand
6140.2Above demand

The cycle figure left out a clock

A 60-second run time gives 60 units per hour while the workstation is producing. The production order repeats a different clock: one setup, then the run work for the whole batch. Every repetition pays that setup again. A capacity figure built from run time alone gives those occupied seconds no place in the denominator.

At the opening batch of 40, the station runs for 2400 seconds and spends another 1800 on setup. It therefore releases 40 units in 4200 seconds, equivalent to 34.3 per hour. The order calls for 40.0 per hour. The nominal rate is above demand while the repeated-cycle rate is below it, using the same station and the same run time.

Spreading the setup over more units raises capacity toward the run-only rate. The curve cannot go above that rate. If demand already equals or exceeds the run-only rate, a positive setup cannot be diluted enough by any finite batch. With no setup, batch size has no effect on capacity at all.

A transfer lot is a different quantity. Moving completed units onward in smaller groups can open overlap between stations while the process batch continues under the same setup. This ledger charges a new setup only when a new process batch begins. The distinction decides which clock changes when someone writes a smaller lot on the sheet.

The calculation and its basis

▾

One occupied cycle

Let Q be batch units, S setup seconds, p run seconds per unit, and D hourly demand. Capacity divides units by all occupied time: C(Q)=3600QS+QpC(Q)=\frac{3600Q}{S+Qp}C(Q)=S+Qp3600Q​. Required load is the fraction of available time the demand would occupy: u=D(S+Qp)3600Qu=\frac{D(S+Qp)}{3600Q}u=3600QD(S+Qp)​.

The strict crossing

Q>DS3600−Dp(3600−Dp>0)Q>\frac{DS}{3600-Dp}\quad(3600-Dp>0)Q>3600−DpDS​(3600−Dp>0). The first whole quantity strictly above the quotient has spare capacity. Equality receives its own reading, and a nonpositive denominator means no finite batch is strictly above demand.

The opening ledger

  1. Run work: 40×60=240040\times60=240040×60=2400 seconds; cycle time: 1800+2400=42001800+2400=42001800+2400=4200 seconds.
  2. Capacity: 3600×404200=34.285714285714285\frac{3600\times40}{4200}=34.28571428571428542003600×40​=34.285714285714285 units/hour, displayed as 34.3; load: 40×42003600×40=1.1666666666666667\frac{40\times4200}{3600\times40}=1.16666666666666673600×4040×4200​=1.1666666666666667, displayed as 116.7%.
  3. Crossing: 40×18003600−40×60=60\frac{40\times1800}{3600-40\times60}=603600−40×6040×1800​=60 units; 60 ties at 40.0 units/hour, and 61 first exceeds demand at 40.21978021978022, displayed as 40.2.

Source basis

Gerard Cachon and Christian Terwiesch derive setup-adjusted batch capacity in Matching Supply with Demand: An Introduction to Operations Management, fourth edition, 2018, chapter 5. Wallace Hopp and Mark Spearman distinguish process batches from transfer batches and describe their capacity effect in Factory Physics, third edition, 2008, section 9.4.2.

Scale
Whole batches checked from 1 to 1,000; continuous guide between them, exact integer comparison
Basis
One sequential workstation, one occupied setup per process batch, identical run time per unit
Assumptions
Repeated identical cycles, constant demand, all completed units counted on the same basis
Model version
1.0.0

The whole record prints. Your browser can save it as a PDF instead of printing it.

This counts repeated setup and run time; it does not choose a batch size or estimate waiting, scrap, or delivery dates.

Related

  • Transfer lots: the next station starts before this one finishesSplit one batch into transfer lots and the next station starts before this one finishes. The overlap is real time back, and it has a price the schedule never shows.
  • Kingman's formula: one more job doubled the waitA bench running at 90% looks busy and behaves fine, right up until it does not. What sets the wait is how full it is, and how unevenly the work arrives.

Setup load record

Setup load: the fast cycle still falls short

Entered production values

Production batch, units (opening value)
40
Demand, units/hour (opening value)
40.0
Run time, seconds/unit (opening value)
60
Setup time, seconds/batch (opening value)
1,800

Capacity reading

Capacity with setups, units/hour
34.3
Required load, percent
116.7
First whole batch above demand
61 units
Whole batch equal to demand
60 units

Numbered calculation trace

1. Run work
40 × 60 = 2,400 seconds
2. Occupied cycle
1,800 + 2,400 = 4,200 seconds
3. Capacity and load
34.3 units/hour; 116.7% required load

This counts repeated setup and run time; it does not choose a batch size or estimate waiting, scrap, or delivery dates.