Capped weekly deduction witness
Liquidated damages cap: the tenth late week costs and the eleventh nothing
Accepted inputs
- Hypothetical monetary basis
- 10,000,000
- Weekly rate
- 0.5 %
- Cap
- 5 %
- Checked week
- 11
Witness results
- Full weekly amount
- 50,000
- Cap amount
- 500,000
- Cumulative amount
- 500,000
- Amount added at checked week
- 0
- Smallest breaker week
- 11
- Last week adding any amount
- 10
- First zero week
- 11
Record fields
- Calculation version
- 1.0.0
- Boundary
- It computes marginal arithmetic from a typed rate, cap, week count, and hypothetical basis. Zero additional deduction does not make lateness lawful or costless, and the result decides no entitlement or contractual effect.
- Permanent refusal
- This counterexample describes only the arithmetic shape of a capped weekly deduction schedule. It never interprets a contract, classifies lateness, decides entitlement, treats delay as excused, combines sections, or identifies other consequences. A zero here means a further deduction of zero under the schedule typed on this page and nothing else.
- Source class
- The public source class is capped delay deduction schedules in supply and construction contracts, described only through a visitor typed rate, cap, and elapsed week structure. No clause, regime, authority, definition, or legal interpretation is reproduced.